BFF INVESTMENT & DEVELOPMENT JSC · TAX ID 0314518321

Construction Progress Update: BFF Factory & Warehouse — May 2026

After two months of focusing on the substructure, the BFF Factory & Warehouse construction site has entered the superstructure phase at a steady pace. General Contractor B has mobilized two additional 60-ton tower cranes and a specialized steel erection team, ensuring progress for both sub-zones A1 and A2 runs in parallel.

May Progress Overview

The strip and isolated foundation systems for the office and auxiliary blocks passed Phase 1 inspection on May 9, 2026. BFF’s independent monitoring department recorded a margin of error within ±3mm, meeting TCVN 9362:2012 standards for industrial construction.

When the substructure finishes two weeks early, it is not luck — it is the result of a meticulous set of design standards and an experienced general contractor.

— P. NGUYEN · PROJECT DIRECTOR, BFF

Completed Milestones

  1. D800 bored piles for the entire A1 zone — 312/312 piles.
  2. Strip foundations for axes 1 → 14, margin of error ±3mm.
  3. Main underground drainage system, D600 diameter.
  4. Erection of steel columns for axes A–F, zone A1 (in progress).
Chat on Zalo